Monday, April 30, 2007

Update on regional planning guidelines

Non-National Roads-Metropolitan Area-Summary Table

http://209.85.165.104/search?q=cache:oi1DtedGlnwJ:www.rpg.ie/documents/JRMRoadsandPublicTransportInfrastructureUpdateNov06.doc+monkstown+ring+road&hl=en&ct=clnk&cd=18&gl=ie

KEY:
Stage 1 = Project in planning/feasibility study underway
Stage 2 = Planning for scheme approved
Stage 3 = Tenders in preparation
Stage 4 = Currently under construction
Stage 5 = Project Completed.

DCC
East Wall Road

Stage 5 = Project Completed.

DCC
Macken Street Bridge

Stage 4 = Currently under construction

DCC
North King Street

Stage 5 = Project Completed.

FCC
Ongar Road

Stage 5 = Project Completed.

FCC
Outer Ring Road- Lucan to N2

Stage 1 = Project in planning/feasibility study underway

SDCC
Outer Ring Road- N7 to Lucan

Stage 4 = Currently under construction

DLR
Dun Laoghaire Port- Improve Access

DLR
Monkstown Ring Road
Stage 3 = Tenders in preparati
on


WCC
Greystones Southern Access

Stage 4 = Currently under construction

East Wall Road (Tolka Quay to Sheriff Street)
Scheme completed mid-2006

Macken Street Bridge
Tenders have been approved and initial groundworks have commenced. It is expected the Bridge will be open in September 2008.

North King Street
Road improvements completed.

Ongar Road
Road completed, opened in December 2005.

Outer Ring Road- Lucan to N2
This project is being undertaken in two phases. Phase 1 linking the N2 to the N3 is approved and will begin construction in 2007 with completion in 2008. Phase 2 links the N2 to the N4. This is currently at plan preparation stage.

Outer Ring Road- N7 to Lucan
Phase 1 (Adamstown to N7) completed and open since January 2005. Phase 2 (Adamstown to N4) is under construction and due for completion in September 2007.

Dun Laoghaire Port- Improve Access
This project requires a feasibility study which has yet to commence.

Monkstown Ring Road
This scheme was approved by An Bord Pleanala in June 2006. Tenders are under preparation. It is intended that construction will commence in early 2007 with a completion in 2008.

Greystones Southern Access
Southern Access road is completed. Works are due to commence on the Kilpedder Interchange where the Access road meets the N11.

Balbriggan Outer Relief Road
This route is currently under construction. The section from Whitehart Lane to Naul Road is due to start works early 2007, with the route scheduled for completion by 2009.